Walthamstow SSL

We recently carried out a Plant room Upgrade for a National Supermarket Chain in Walthamstow. The works comprised of fitting 2 new Hamworthy Wessex ModuMax mk3 boilers alongside the existing Hamworthy boilers.

Our welders had to fabricate a number of spool pieces to enable us to connect to the Imperial Table D flanges. We also had to fabricate a 6inch header to which all 4 boilers then connected on to. The gas run on this installation was all carried out in 108mm Geberit Mapress Stainless and was slightly challenging as we had to run this on the underside of the first floor slab, this was all carried out on a SkyJack SJ19 which greatly helped in reducing the installation time.

The heating coil that serves the shop floor air handling unit was also changed over during these works and we’re happy with the finish of this project.